Edit Resource: DurOverrideEfficiency
Format
SCHED / EditResource '<ResourceName>' DurOverrideEfficiency <Value>
Description
The DurOverrideFixed attribute under EditResource defines the efficiency factor of the override for the resources with DurationOverrideType = EfficiencyFactor.
Parameters
Parameter | Description |
---|---|
Value | The efficiency factor as a decimal. |
Examples
The resource will override a task's duration based on an efficiency factor of 1.3. If a task with a 60s duration uses OpsTeam, the task duration will now be 46s.
SCHED / EditResource 'OpsTeam' DurOverrideEfficiency 1.3